Current Chain Hoist Lead Times

Due to continued supply chain disturbances from the Covid pandemic, current lead times are as follows:

Updated 10/3/2022

Fastest Options Highlighted in GREEN

SINGLE-PHASE CHAIN HOISTS    (115/1/60, 230/1/60)

Budgit (Single-Phase)...........................................Manufacturing operations on indefinite hold

CM Lodestar NH & Classic (Single-Phase)......180 business days (36 weeks)

**CM Lodestar VS (Single-Phase)........................120 business days (24 weeks)*

**CALL FOR QUOTE  800-724-4052 x101. 

Coffing JLC (Single-Phase)..................................180 business days (36 weeks)

Coffing EC (Single-Phase)....................................180 business days (36 weeks) *Call for Quote*

 

THREE-PHASE CHAIN HOISTS  (208/3/60, 230/3/60, 460-480/3/60)

Budgit (Three-Phase)..........................................Manufacturing operations on indefinite hold

CM Lodestar NH & Classic (Three-Phase)........120 business days (24 weeks)

CM Lodestar VS (Three-Phase)............................120 business days (24 weeks)

**Coffing JLC (Three-Phase).................................60 business days (12 weeks)

Coffing EC (Three-Phase)......................................60 business days (12 weeks) *Call for quote*

 

Questions? Call Jon at 800-724-4052 ext. 101

 